LEI Portfolio

portfolio > Office-Retail > Unigard Business Park, Phase III

Unigard Business Park, Phase III


Bellevue, Washington

PDF Download

Unigard Business Park, Phase III: Scott Sherrow PE served as project manager/lead engineer for the expansion of this 47-acre business park. Project tasks included assisting in the pre-planning exercise and Public Hearing Process to develop a conceptual plan consistent with client needs, which could be supported by the local residential communities and the City of Bellevue's Department of Land Use.

Project surveying tasks included the coordination of the project's topographic and boundary survey needs, preparation of the lot segregation documents, site condominium documents, assorted site legal descriptions, and construction staking.

unigardInline.JPG

On-site work included design of grading, storm drainage conveyance system, water and sanitary sewer systems, geometric layout/parking lot, design coordination, and construction support services. Work also included renovating the site's storm detention facilities to serve existing buildings on-site, and expanding the facilities to serve the new 5 multi story building complex and the underground parking garage.

Off-site work involved reconstruction of the frontage arterial including sanitary sewer and water main improvements.

Project services included construction support, surveying, land segregation, construction staking, and on and off-site civil design. All permit applications were prepared and tracked on the owner’s behalf, including state/governmental permits.

(Project Experience by Scott Sherrow and\or Laren Bailey)

Project Experience


  • Pre- Planning
  • Topographic Survey
  • Boundary Survey
  • Condominium Documents
  • Finial Plat
  • Civil Design:
    • Site Grading
    • Stormwater Management
    • Water Distribution Design
    • Sewer Collection System
    • Off-Site Road Improvements
  • Construction Observation
  • Construction Administration